|
dhaslam
|
 |
« on: September 19, 2010, 04:18:43 PM » |
|
At last starting to make some progress.
The straw arrived on Saturday. 100 bales in the car port for wrapping and the other 300 in a covered stack. The silage pit cover will be used to cover the finished mound. The solar panels are stacked up waiting for the Correx sheets to arrive. The 100mm sewer pipes are for the air feed to the Correx sheets and the 150mm ones to hold the four lengths of 22mm pipe bringing hot water back to the house, they just about fit with two layers of pipe insulation on each. The heat transfer will be into two 150 metre coils of 38mm hydrodare. The inner one is intended for direct transfer to the buffer tank and the outer one to preheat the ASHP.
Each collector will heat its own layer with the outer ones heating the top and bottom layers. There will be one 60watt fan for each collector and each one will have its own thermostat for flow temperature and one wire sensor for the core temperature. The fans will probably be set for about 10 degrees above the core temperature for it's respective layer but this may need to be adjusted. If the temperature differential is too low the heat gain may not be much more than the electricity used and if it is too high the fans may not come on very often. There is no need to be interactive because the temperature will change very slowly.
Should be ready to work by the end of the week.
|
|
|
|
Logged
|
|
|
|
|
desperate
Guest
|
 |
« Reply #1 on: September 19, 2010, 04:28:27 PM » |
|
DHaslam,
very impressive undertaking there, keep us informed of progress and eventually performance. This is the type of project I would love to be able to carry out, there is vast potential in such a system if it were to be incorporated into newbuilds in a holistic way.
My back aches just looking at that huge pile of gear you have there.
Good luck
Desperate
|
|
|
|
|
Logged
|
|
|
|
|
billi
|
 |
« Reply #2 on: September 19, 2010, 05:48:22 PM » |
|
... nice and i am looking forward
Is the subsoil called " Blue till" as well like here in West cork ? and will you compact it ?
Pity you are so far away from me and my digger
how much are straw bales atm ?
Billi
|
|
|
|
|
Logged
|
Guinness no Grid comes near
1.6 kw and 2.4 kw PV array , Outback MX 60 and FM80 charge controller ,24 volt 1600 AH Battery ,6 Kw Victron inverter charger, 1.1 kw high head hydro turbine as a back up generator , 5 kw woodburner, 36 solar tubes with 360 l water tank, 1.6 kw windturbine
|
|
|
Fiddlers
Jr. Member

Offline
Posts: 90
|
 |
« Reply #3 on: September 19, 2010, 09:23:59 PM » |
|
I'm intrigued and missed previous discussions on this one... any chance you could recap the basic design? capacity? I presume you're using water as the storage medium? looks like a great experiment!
|
|
|
|
|
Logged
|
|
|
|
|
dhaslam
|
 |
« Reply #4 on: September 19, 2010, 11:34:28 PM » |
|
The ground is a bit unusual, there are successive layers of limestone separated by heavy subsoil. The lower layers are harder to break up so the test hole was done just to see how far the JCB could go. It is probably sufficient to go down three bales deep, just over a metre. The circle is nine metres at present. There will be six bales above ground but above ground they will be stepped gradually so the volume will be about 180 cubic metres. This is roughly the equivalent of 45,000 litres of water. There will be a lot of rock which helps heat storage capacity and will help prevent compaction. The greenhouse job done earlier this year had 2.5 metre deep heat store filled in by hand and it didn't compact noticeably. Bales are €2 at present plus delivery. The bales offered for sale are loosely packed which seems to be OK for insulation purposes.
The concept is probably a little different than most seasonal stores. Hot air is used as to heat the store. Air is more manageable than water, no problems with freezing and boiling and quite easy to collect the heat. But since air stores something like 3000 times less heat than water, by volume, it is hard to transfer the heat except for very short distances. Consequently water pipes are used to transfer the heat from the store to the house and a heat exchanger used to transfer heat back to air to preheat the ASHP. It does mean a lot of pipes and plumbing fittings with effectively two systems but the hot air collectors are very inexpensive and seem to be more efficient than low grade hot water collectors.
May be able to test run a collector in the few days.
|
|
|
|
|
Logged
|
|
|
|
|
dhaslam
|
 |
« Reply #5 on: October 03, 2010, 10:42:51 PM » |
|
Finally got a one of the collectors working. Hans who is doing most of the work picked up flu last week, possibly from adverse working conditions in a draughty carport.
The panels are very heavy when everything is fitted. and it meant using the car trailer with the sides off to move one. It is leaning on a pile of sand at slightly too low angle. After running continuously for quite a while the output temperature built up to over 60C with input air of about 40C less. It sound an feels like a giant hair drier. The face of the panel stays quite cool and all the heat is inside the 6mm square channels. Even with the fan off there is a strong flow of hot air. Assuming that the fan is putting out close to its maximum of 280 cu metres/hour it is producing about 3kW, in October broken sunshine. In comparison the Navitron panels of similar area output 16 kWh for the day. Even in overcast conditions with the sun just visible through the clouds the output temperature was in the high 30sC.
It looks like the fans will have to be moved to the input side of the panel next summer because they probably couldn't take the full summer heat directly from the panel. The thermostats will have to be moved away from the fans to a separate position on the output side. They should be OK for the winter but the temperature drop when running the fan is much less than expected.
The fan is causing the plastic cover to sag due to some small gaps between the 4" pipe and the Corex sheets. The next ones have three supports for the cover and also may have a bit less air leak. The first one had one pipes cut with a jigsaw and the second with a router, both were a bit uneven so the Corex sheets weren't a tight fit. The next one was cut with a skilsaw and a guide running along the side of the frame. This made a very even cut.
The store is due to be constructed tomorrow, weather is supposed to be the same as today, sunny in the morning and then showers. I will probably set up the panels that are made so that there is some feedback on the temperature rise before completing the others.
|
|
|
|
Logged
|
|
|
|
|
biff
|
 |
« Reply #6 on: October 04, 2010, 09:26:05 PM » |
|
hi dhaslam, really good thread,and i am looking forward to seeing more of this solar project, biff
|
|
|
|
|
Logged
|
|
|
|
|
dhaslam
|
 |
« Reply #7 on: October 05, 2010, 12:59:34 AM » |
|
Some progress today but only up to ground level so far. One layer of pipes installed. It is surprising how difficult it is to handle 150 metres of 1.5" hydrodare. It may be possible to finish the store tomorrow but each layer of fill is taking quite a long time and the fill needs to be on both sides of the bales to avoid pushing them out.
|
|
|
|
|
|
djh
|
 |
« Reply #8 on: October 05, 2010, 11:51:43 AM » |
|
Do you have any photos showing how the bales are arranged and filled around?
|
|
|
|
|
Logged
|
Cheers, Dave
|
|
|
|
dhaslam
|
 |
« Reply #9 on: October 05, 2010, 09:35:24 PM » |
|
Do you have any photos showing how the bales are arranged and filled around?
The bales are wrapped for the first three rows. The two lower rows are wrapped in heavier plastic, the row just visible is mostly out of the ground om one side because of the ground level being lower. I have decided to reduce the numbetr of rows of bales to seven in total, one more row than is visible in this photograph and to dome the clay in the centre and the covering bales will then be on a slight slope. chargingtheearth There was a bit of constructive criticism previously, relating to using bales underground. The main precautions taken since then are wrapping the bales underground and putting in a drainage pipe all around the mound. Inevitably there is always going to be some constructive criticism but the valuable benefit from any forum is the expansion of ideas. The heat loss from the mound will be quite large and that will be known reasonably soon by plotting the daily temperatures, probably just morning and evening.I am hoping that the large area of solar collector will make up for the heat loss but if temperatures are not very high at will at least achieve its initial function of pre heating the ASHP as well as supply some underfloor heating.
|
|
|
|
|
|
guydewdney
|
 |
« Reply #10 on: October 05, 2010, 10:34:32 PM » |
|
When I have seen straw bale houses done - they are very careful to close up any small gaps between bales - could you not do the same - or are you planning to fill the gaps with expandy foam or something?
|
|
|
|
|
Logged
|
|
|
|
|
dhaslam
|
 |
« Reply #11 on: October 05, 2010, 10:52:54 PM » |
|
Just broke up a few bales to pack the bigger gaps. It won't be that much of a problem because there will be several feet of clay outside the bales.
|
|
|
|
|
Logged
|
|
|
|
|
djh
|
 |
« Reply #12 on: October 06, 2010, 10:19:53 AM » |
|
The bales are wrapped for the first three rows. The two lower rows are wrapped in heavier plastic, Thanks very much for the piccy. It looks like the bales might be wrapped individually; is that the case or is the whole wall wrapped as one? There was a bit of constructive criticism previously, relating to using bales underground. That's a very generous description, thanks!  I have to say that I still think they're likely to rot, but full marks to you for actually getting out there and trying it. I'd suggest sticking a few moisture meters in there. In the middle of the bales, towards the bottom. I suspect you can just push a rod/pipe through the bales to get them in. I think the easiest type is a block of wood a couple of inches long, with wires trapped under stainless steel screws in the wood. Then connect the other end of the wires to a regular pin-type wood moisture meter whenever you want to take a reading. Edit: I forgot to mention that it needs to be electrically isolated from the straw. So either silicone seal over the screws or put the whole piece of wood inside a perforated box or length of tube.
|
|
|
|
« Last Edit: October 07, 2010, 01:25:57 PM by djh »
|
Logged
|
Cheers, Dave
|
|
|
|
dhaslam
|
 |
« Reply #13 on: October 06, 2010, 10:08:40 PM » |
|
The bales are individually wrapped up to ground level and the ones above ground will just have an overall cover over the top. At present I am a bit more concerned about the unwrapped ones because they will absorb trapped moisture from the clay. I need to measure the moisture content of the return air from the mound and see if the humidity is reducing. If not I can reduce moisture by leaving the return pipes open to the air for a few hot days next summer. The input from the five collectors may be as 25 kW on a very hot day in summer and the pipes are perforated drainage pipes. This would also help dry out the soil below ground level where the wrapped bales are. Storage capacity would be higher if the soil is moist but insulation and preservation of the straw would be better if the soil is dry.
|
|
|
|
|
Logged
|
|
|
|
|
dhaslam
|
 |
« Reply #14 on: October 17, 2010, 08:12:15 PM » |
|
Finally got the panels mounted on Thursday last and the first panels heating on Friday and the next two nos two and three numbered from east to west and from lowest to highest. Oddly enough it seems to have slowed the rate of heating instead of speeding it up. The initial heat may be from settling of the clay. There was very good sun on Saturday with temperatures reaching over 70C but the return air to the panels didn't go over 17C so the heat is being dissipated very quickly, probably before reaching the core where the sensors are at each level. The pipes are not fully insulated before going into the mound so some heat is being lost outside the insulation layer. Unfortunately these pipes cannot be dug out until the clay binds on the sides, otherwise it would just move down and fill the space dug out. It will need to be done before next summer. For this winter the system will only be used to preheat the heat pump input and this cannot be connected yet because a drain has to be made all around the mound to take away the rain water. The present temperature is probably enough to warm the air if it holds at this through the winter. 
|
|
|
|
Logged
|
|
|
|
|