tange179
|
 |
« on: April 20, 2011, 01:32:10 PM » |
|
Hi All,
Anybody recieved payment from SE from March 31st (2011) reads yet?
John.
|
|
|
|
|
Logged
|
|
|
|
|
skyewright
|
 |
« Reply #1 on: April 20, 2011, 02:40:37 PM » |
|
Anybody recieved payment from SE from March 31st (2011) reads yet?
We've received an invoice/statement from SSE based on our 31/03/2011 readings. Last time around the payment appeared in our bank about 10-14 days after the invoce/statment.
|
|
|
|
|
Logged
|
Regards David 3.91kWp PV (17 x Moser Baer 230 and Aurora PVI-3.6-OUTD-S-UK), slope 40°, WSW, Lat 57° 9' (Isle of Skye)
|
|
|
|
Iain
|
 |
« Reply #2 on: April 20, 2011, 07:50:44 PM » |
|
Hi Nothing from SSE yet. Haven't chased them up yet though. (John, sorry I didnt reply to your PM) Iain
|
|
|
|
|
Logged
|
1.98kWp PV (11 x Sharp 180 and SB1700) 20 x 65mm Thermal and 180ltr unvented 6000ltr rainwater storage Plymouth
|
|
|
|
tange179
|
 |
« Reply #3 on: April 21, 2011, 09:16:51 AM » |
|
I have spoke to them on the dog & bone, and: Firstly they have changed me from cheque to BACS credit  Secondly they have said that payment can be anytime before the next read date on the 30th June  When I get my nxt import bill prehaps I will offer them the same - "I will pay you sometime within the next 3 month's" - somehow I do not think they will be too happy with this statement  John
|
|
|
|
|
Logged
|
|
|
|
|
Iain
|
 |
« Reply #4 on: April 21, 2011, 11:11:05 AM » |
|
Hi Just phoned, a very helpful chap at SSE. He talked to the payments team and they processed it there and then, very impressed. Cheque within 10 days. I think they have quite a backlog but the Customer Services were 100% Iain
|
|
|
|
|
Logged
|
1.98kWp PV (11 x Sharp 180 and SB1700) 20 x 65mm Thermal and 180ltr unvented 6000ltr rainwater storage Plymouth
|
|
|
|
skyewright
|
 |
« Reply #5 on: April 21, 2011, 12:04:10 PM » |
|
Secondly they have said that payment can be anytime before the next read date on the 30th June  "Payment within 13 weeks" seems to be part of their standard terms & conditions? Hopefully it's just there as a "let's cover our backs just in case we get totally overwhelmed" clause...
|
|
|
|
|
Logged
|
Regards David 3.91kWp PV (17 x Moser Baer 230 and Aurora PVI-3.6-OUTD-S-UK), slope 40°, WSW, Lat 57° 9' (Isle of Skye)
|
|
|
|
tange179
|
 |
« Reply #6 on: April 29, 2011, 05:20:08 PM » |
|
Well posty gave me a surprise on Thursday.......my second FIT payment  Roll on June/July - should be a good one with all these extra april photons  John
|
|
|
|
|
Logged
|
|
|
|
|
greentangerine
|
 |
« Reply #7 on: April 29, 2011, 06:14:06 PM » |
|
Been with EON for the FITs since the start and they have always paid promptly.
Sent my reading off by email on the 1st April, payment received in my bank on the 20th.
Haven't checked the contract to see if it specifies the timescale they allow themselves to pay me.
|
|
|
|
|
Logged
|
2.94 kWP (Sharp ND210 / SB2500) 65 x Ø58mm SunnPro / Torrent T280 RE OV 11kW Dean Forge Croft Clearburn with 10,000 BTU boiler.
|
|
|
|
Iain
|
 |
« Reply #8 on: May 03, 2011, 12:19:47 PM » |
|
Hi All Have just received my FIT invoice for the last 1/4 from SSE. "Cheque to follow"!!!. But on the invoice they have deemed export of 50% up until 28th Jan 11 and then it is metered export. So it seems that the Export meter reading is finally being used (28th Jan onwards) Iain
|
|
|
|
|
Logged
|
1.98kWp PV (11 x Sharp 180 and SB1700) 20 x 65mm Thermal and 180ltr unvented 6000ltr rainwater storage Plymouth
|
|
|
|
Iain
|
 |
« Reply #9 on: May 05, 2011, 05:45:14 PM » |
|
Cheque arrived today Iain
|
|
|
|
|
Logged
|
1.98kWp PV (11 x Sharp 180 and SB1700) 20 x 65mm Thermal and 180ltr unvented 6000ltr rainwater storage Plymouth
|
|
|
|
russ_fae_fyvie
|
 |
« Reply #10 on: May 24, 2011, 09:34:20 PM » |
|
I'm still waiting !!! 
|
|
|
|
|
Logged
|
Sunny Island 3324, Sunny Boy 1700, Rolls Battery Bank, SDMO Backup Genny, 1.44kW PV Array, 1kW Futurenergy Turbine, now more grey hair !
|
|
|
|
marshman
|
 |
« Reply #11 on: May 24, 2011, 10:20:01 PM » |
|
Sent SSE my meter readings by email on March 31st at 6:00PM. Heard nothing until May 13th when I received a statement in the post saying payment by cheque would follow. Money was paid into my bank today by BACS!!! Took 7 1/2 weeks. Better than last quarter which took the full 13 weeks!
Roger
|
|
|
|
|
Logged
|
3.15kWpk (15xSharp ND210)/SB3000. & 3.675kWpk (15 x Suntech 245WD)/SB4000TL, Futurenergy FE1048 turbine/2 x Windmaster 500. Hunter Midi 20 wood burner with boiler driving Wirsbo underfloor heating. 10' x 7' solar wall (experimental)
|
|
|
|
ecogeorge
|
 |
« Reply #12 on: May 24, 2011, 10:50:24 PM » |
|
Still waiting for Goodenergy FIT , but they have assured me it will be in the bank this week! Will keep you updated. George.
|
|
|
|
|
Logged
|
|
|
|
kittie
Newbie
Offline
Posts: 2
|
 |
« Reply #13 on: May 26, 2011, 06:19:23 AM » |
|
I am still waiting for goodenergy too. They are very slow
|
|
|
|
|
Logged
|
|
|
|
|
Justme
|
 |
« Reply #14 on: May 26, 2011, 09:07:51 AM » |
|
I am still waiting for goodenergy too. They are very slow
The reason they pay slower is that they are not a primary FIT supplier. So they have to wait for the balancing to be done. Balancing is where all the FIT utillities "pool" the kWh generated & then re distribute the levi on util bills to match the generated power. As Good energy will be paying more out in FIT's than they make on the levi they have to wait for the balancing to be done. Bigger utils can pay out as they will get more in the levi than they pay out.
|
|
|
|
|
Logged
|
Navitron solar thermal system 30 x 58mm panel 259L TS 1200watts solar 120vdc FX80 Solar controller Victron 12v 3000w 120a 200w (250w peak) 12v turbine as a tester 6kva genny 6 x 2v cells 1550amp/h 5C 24 x 2v cells 700amp/h 5C Total bank 4350 amp/h @12v
|
|
|
|