Connecting any small scale electrical generator (SSEG), such as PV, wind, hydro or CHP, in parallel to the UK grid is governed by several interlocking pieces of legislation.
Engineering Recommendation G83/1-1 (referred to as G83 below) is the current set of rules that apply to the connection of SSEGs to the public electricity network. It has been drawn up, and continues to be developed, by a working group of the Distribution Code Review Panel (DCRP) formed under the control of the Energy Networks Association (ENA), a body made up mostly of members of the Distribution Network Operators (DNOs).
G83 is an annex to the UK Distribution Code which, in turn, is developed under the auspices of the Electricity Safety, Quality and Continuity Regulations (ESQCRs) as enacted by parliament. Any changes made to G83 are required to be approved and promulgated by OFGEM, who are responsible for overseeing the whole regulatory process.
The ESQCRs state that all systems, with one exemption, can be connected to the grid only with the prior approval of the DNO. The exemption applies in the case of an SSEG up to 16A per phase and where that system complies with the requirements of both G83 and BS7671. In this case you can connect the system and then tell the DNO when it is complete.
DNOs are allowed to apply discretion regarding the 16A limit where, based upon their detailed local knowledge, they are happy that the network can cope with a higher figure and that no detrimental effects will result for neighbouring properties.
There are some circumstances where an SSEG connection under G83 may be denied by a DNO, such as multiple SSEGs connected on a single transformer. Prior discussion with the DNO is the only sure way to find out if this applies in a particular case.
If you are planning to install an SSEG larger than 16A per phase then you must contact your DNO before you install the system. They may require a network survey to be conducted (at your expense) before agreeing that you can go ahead.
The ESQCRs empower the DNO to disconnect any property from the grid if they are not happy that the installation complies with the regulations.
G83 covers both the type-testing of particular products, such as inverters, to ensure that these comply with the appropriate technical requirements and also to the complete installation of a SSEG. Type tests are usually arranged by product manufacturers and have to be carried out by suitably accredited test labs and these labs may be in-house (for the larger manufacturers) or separate commercial operations.
When you purchase an inverter you should make sure that you get a copy of the G83 test certificate from the supplier. Some manufacturers have copies which can be downloaded from their websites.
Details of the type of tests covered by G83 can be gleaned from the Type Verification Test Sheet - see ref below.
When an SSEG is installed the electrician responsible must complete and sign a commissioning certificate to confirm that the complete system complies with G83. The system owner needs to keep a copy of this and a second copy must be sent to the DNO. The completed paperwork must be submitted to the DNO within 30 days of the system being commissioned.
Other countries have similar, but not identical, regulations to G83. Germany, for example, has DIN VDE 0126 and Australia has something called AS 4777.
Ireland have decided to make use of G83 rather than going to the trouble of developing their own separate regulations.
In recent years there has been an effort to bring about wider EU and global harmonisation in this area through CENELEC and IEC. The same UK engineers who have developed G83 have been in the working group to develop EN 50438. Not surprisingly, as the UK has taken the lead in this, it generally embodies all the same requirements as G83.
Refs:
DCRP Constitution -
http://www.energynetworks.org/dcode/pdfs/GBDCRP%20Constitution%20and%20Standard%20Procedures%20October%202009.pdfDNO Contact details -
http://www.energynetworks.org/engineering/pdfs/DG/DistributorNetworkOperatorContactDetails_071114.pdfElectrical Safety, Quality and Continuity Regulations 2002 -
http://www.opsi.gov.uk/si/si2002/20022665.htmENA -
www.energynetworks.orgGrid Code -
http://www.nationalgrid.com/NR/rdonlyres/67374C36-1635-42E8-A2B8-B7B8B9AF2408/35187/Complete_I4GridCode.pdfG83/1 Type Verification Test Sheet -
http://2010.energynetworks.org/storage/engineering/ER_G3-1_Appendix_4.docInternational Harmonization of Islanding Prevention Requirements, Woyte et al, 2003, http://www.kuleuven.be/ei/Public/publications/EIWP03-09.pdf
Technical Guide to the Connection of Generation to the Distribution Network -
http://www.energynetworks.org/engineering/pdfs/DG/FES_00318_v040211.pdfThe Distribution Code of Great Britain -
http://www.dcode.org.uk/Western Power - Connection Considerations for Distributed Generation -
http://www.westernpower.co.uk/getdoc/8269db62-16ed-4fe2-ae7f-82ae794aeece/Connection-Considerations-for-Distributed-Generati.aspxWestern Power - Connection Considerations for Small Scale Embedded Generators -
http://www.westernpower.co.uk/getdoc/3d0c88f4-7010-44c6-aa7b-7b78c44af0ce/Connection_considerations_for_small_scale_embedded.aspxWestern Power - SSEG Installation Commissioning Confirmation -
http://www.westernpower.co.uk/getdoc/26ee74bb-96be-48ca-b5a1-4bfe88eb4f51/Installation_Commissioning_Confirmation_Form.aspxCopies of G83 are available for purchase from
http://www.ena-eng.org/ENA-Docs/eadocs.asp?WCI=DocumentDetail&DocumentID=8016[edit - made a sticky]